Method Statement For Gypsum False Ceiling Work

Construction site showing exposed GI grid framework for gypsum false ceiling installation, with ladder, scaffolding, gypsum boards, and the method statement title displayed across the image. qa/qc in construction

This Method Statement For Gypsum False Ceiling Work outlines the systematic procedure, quality requirements, materials, tools, and safety measures for the installation of Gypsum/Calcium Silicate False Ceiling works. It ensures that all activities are executed in accordance with approved drawings, manufacturer guidelines, and project specifications, thereby achieving a safe, durable, and high-quality ceiling finish.

1. Purpose

The purpose of this document is to detail the Procedure for Gypsum False Ceiling works as per the approved details. The documentation will apply to all Engineers, Workmen, QC personnel and other concerned persons associated with the work.

2. Scope of Work

This method covers the preparation, installation, finishing, inspection, and safety precautions associated with Gypsum/Calcium Silicate False Ceiling work.

Exposed GI framework and gypsum board installation in progress at a real construction site, with ladder, scaffolding, wiring, and stacked boards on the floor.
Gypsum false ceiling framework under installation at a live construction site, showing GI framing, wiring, and board preparation.

3. References & Standards

  • Drawings and any other relevant/applicable documents.
  • Project technical specifications
  • IS 2095 (Part 1) – 2011
  • IS 513
  • ASTM C475
  • MSDS
  • Manufacturer’s recommendations
  • GRIHA Requirements
  • HIRA
  • Respective Indian standards
  • Inspection and test plan for Block work

4. Materials

  • 12.5 mm Gypsum Board / 8 mm Calcium Silicate Board (Approved make as per IS 2095 Part 1)
  • GI Framing sections conforming to IS 513
  • Jointing compound conforming to ASTM C475
  • Screws, cleats, channels, connecting clips

5. Material Delivery & Storage

  • Transport all materials safely to avoid damage.
  • Damaged materials shall be rejected.
  • Store boards on raised platforms, protected from moisture.
  • Store items close to the execution area to reduce handling.
  • Maintain proper stacking and protection during storage.

6. Manpower

  • Project Engineer
  • Site Engineers
  • Supervisors
  • Foremen
  • QC Inspectors
  • Skilled Masons
  • Helpers
  • Safety Officer

7. Responsibilities

The Project Manager/Construction Manager is responsible for the full execution of this method statement. Site Engineers shall ensure proper layout, supervision, and adherence to quality. QC Engineers shall inspect materials and verify compliance. Safety officers shall enforce safety measures.

8. Equipment & Tools

  • Drilling machine & drill bits
  • Scaffolding
  • Cutting tools / Board cutter
  • Self-levelling laser
  • Circular saw & blades
  • Hammer
  • Measuring tape

9. Work Procedure

Sign up to download the full customizable Method Statement for Gypsum False Ceiling works in Word format